
MID-ATLANTIC CONTINGENCY PLANNING
GROUP
May 4, 2005
The spring meeting of the
Mid-Atlantic Contingency Planning Group was held at the Stonewall Resort in Roanoke,
West Virginia and hosted by Columbia Gas Transmission. Todd Smith called the meeting to order at
1:15 p.m.
The following were in attendance:
Chairman: Todd
Smith (Roanoke Gas)
Vice Chairman: Tom
Gibson (Columbia Distribution)
Secretary: Drew
Moncol (VA Power) unable to attend
Ed Unger South
Jersey Gas
Barry Ranson Dominion
Jody Derrickson Dominion
Ed Turowski Baltimore
G & E
Rich Truxell Williams-Transco
Wayne Rutledge AGL
Resources
Jim Cosgrove Washington
Gas
Andrea Mills Washington
Gas
P. Scott Murphy Washington
Gas
Michael Gagnet Roanoke
Gas
Bill Christian Columbia
Gas Transmission
Gale Carovillano Columbia
Gas Transmission
Sharon Burdette Columbia
Gas Transmission
Al Dillard Columbia
Gas Transmission
George Smith Virginia
Power
Columbia Gas Transmission Gale Carovillano reported
that temperatures throughout Columbias operating areas were 2.7% warmer than
normal compared to 2.5% for last year.
Total throughput was 682.0
Bcf. Peak day occurred on January 23rd
with a throughput of 7.0 Bcf. FSS
customers withdrew approximately 4.3 Bcf and the weighted average temperature
for the day was 11°.
Storage customers started the season with 96.7% of their SCQ and
ended at 18.2%. They withdrew 192.0 Bcf
in total this winter compared to 197.0 Bcf last year. Columbia anticipates no issues for FSS customers planning to
inject up to their full SCQ.
Upcoming projects include approximately 952 miles of
pipeline scheduled for smart pigging throughout
the system. Projects affecting the
mid-Atlantic area are: Line MA from
Linden Church to Rutledge and Line MB from Potomac River to Owings Mills will
undergo installation of launchers and receivers, etc. to make the lines
pigable. Lines VC and MC will undergo
baseline assessment with geo and smart pigging from Loudoun to Linden
Church. Several sections of Lines VB, VB-Loop and VB-5 are scheduled for
recoating between Strasburg and Nineveh.
Also, a shrink sleeve replacement on Line VB-5 downstream of Nineveh.
Girth weld coating remediation is scheduled on Line WB-5 from
Glady to Whitmer. Launcher and receiver
will be installed for geo and smart pigs on WB-Loop 26.
In April, uprating on Line VA-20 was completed from Gala to
Lexington. The line was restored to
original MAOP of 1000# and unit #3 at Gala compressor station was modified to
increase operating envelope. Smart pig
was run from Lexington to Bickers and at Bickers c/s, replacement of the filter/separator
on the suction line.
Smart pig inspections and remediations continue on Lines SM-80
and SM-80 Loop between Ceredo and Lanham compressor stations.
Williams-Transco The peak day for the 2004/05 winter
season occurred on December 20, 2004.
Total market area deliveries for this day were 8,740 MDT. The peak day for last winter was 7,973 MDT
set on January 26, 2004. The three
consecutive day peak occurred on January 17, 18, 19 with a 3 day delivery average
of 8,370 MDT/day.
All facilities operated as designed throughout the winter
period.
Construction and maintenance planned in the Mid-Atlantic region
include Clean Air Act modifications (HPFI) at various compressor stations. Station 170 near Appomattox, Virginia is
scheduled to have 1-2 units down this summer/fall. A complete station outage (24 hours) is planned for early
spring. No impact on shippers
anticipated.
Hydrostatic test on 42 inch Main Line D between the Potomac
River, Maryland (MP1603.97) (Montgomery County) and Compressor Station 190 near
Ellicott City, Maryland (MP 1628.78) (Howard County). Estimated outage timing:
June 6 to June 16, 2005.
In-Line inspection projects include smart pigging 20 miles of
30-inch Main Line A from Compressor Station 185 near Manassas, Virginia (MP
1583.43) (Prince William County) to the Potomac River, Virginia (MP 1603.97
(Fairfax County). Estimated timing for
smart pig runs: May 10 and May 24,
2005. Estimated outage timing for
anomaly repairs, if required: August 5
through August 19, 2005, exact schedule to be determined based on analysis of
smart pig results.
Smart pig 24 miles of 30-inch Main Line A from the Potomac
River, Maryland (MP 1603.97) (Montgomery County) to Compressor Station 190 near
Ellicott City, Maryland (MP 1628.78) (Howard County). Estimated timing for smart pig runs: April 25 and May 12, 2005.
Estimated outage timing for anomaly repairs, if required: August 20 through September 8, 2005, exact
schedule to be determined based on analysis of smart pig results.
Smart pig 64 miles of 36-inch Main Line C from Compressor
Station 195 near Delta, Pennsylvania (MP 1674.58) (York County) through
Compressor Station 200 near Frazer, Pennsylvania (MP 1722.24) (Chester County)
to Main Line Valve (MLV) 200C10, MP 1738.95 in Montgomery County, Pennsylvania. Preparatory work is required to install a
pig launcher and receiver and replace a valve.
Installation of a second launcher at MLV200C10 will extend the outage to
MLV200C20. Estimated time for
preparatory work: from May 21 through
July 8, 2005. Estimated timing for
smart pig runs: July 26 and August 9,
2005. Estimated outage timing for
anomaly repairs, if required: September
26 through November 10, 2005, exact schedule to be determined based on analysis
of smart pig results.
Dominion Winter season was warmer than normal with peak day
occurring on January 18th with a total throughput of 8.7 Bcf as reported by Jody Derrickson. Customer storage levels as of November 1
were 98% and ending March 31 at approximately 26%. Storage turn was approximately 215 bcf for customers and an
additional 80 bcf for storage partners.
No emergency outages occurred during the season but 2 OFOs were
issued dealing with pipeline usage in New York State. Dominion met all firm customer obligations.
Pipeline and storage compressors were available all winter with
very little unplanned downtime. Two new
compressor stations were built and horsepower added to three existing stations
increasing horsepower from 26,400 to 65,600 for deliveries to PL-1 market. Completed and tested the two new compressor
stations with approximately 18,000 horsepower associated with Cove Point East
project. These stations were designed
to move gas from Transco (Pleasant Valley) and Columbia and DTI (Loudoun) into
the Cove Point Pipeline.
Cove Point LNG received 35 LNG tankers containing over 100 bcf
of gas from November 2004 through March 2005.
This liquid was vaporized and served the East Coast markets.
Spring storage tests have been completed and customers will need
to average approximately 1.0 bcf per day injections to refill storage.
Issues affecting operations are pipeline relocation of PL1 3000
of 30 pipe requiring 1 to 2 day outage for tie-ins and construction for
pipeline integrity work on TL-523 Pleasant Valley to Cedar Springs
launcher/receivers installed, 5 days (24 hours a day).
Filing was made in April for Cove Point expansion which will
increase sendout from 1.0 bcf/d to 1.8 bcf/d. 6.8 bcf of additional tank
storage for a total of 14.6 bcf, new pipe and partial looping of 36 line, 2
new compressor stations and additional conventional storage.
Chalk Point Power Station has returned to service with the
addition of the Aquasco M&R recently put in service off the Cove Point
pipeline.
Roanoke Gas Mike Gagnet reported warmer than normal winter
temperatures resulted in 6% below normal volumes for Roanoke Gas and 12% below
normal volumes for Bluefield Gas.
Roanoke, however, experienced its 3rd highest peak day at 85,000 Dth.
Storage ending balances were:
TCO 22-23%, TGP 40% and LNG 50%.
Summer construction plans include LNG fire protection and ESD to
meet NFPA59A.codes.
Columbia of Virginia/Maryland Tom Gibson reported warmer
than normal temperatures for both CMD and CVA.
Peak day occurred for both companies on January 23rd. Throughput for CMD was 54,251 Dth with
average temperature at 12° and
throughput for CVA was 409,337 with average temperature at 18°. Total throughput for the season was down 3%
from last year for CMD and down 4% from last year for CVA.
CMD began the season with 95% of SCQ and ended with 23%. CVA began the season with 99% of SCQ and
ended with 23%.
Due to the construction growth in northern Virginia, companies
expect customer base to increase in excess of 5%.
Washington Gas Scott Murphy stated that this winter
marked the 4th consecutive start to the season with above normal
temperatures. December temperatures
varied with well above normal the first 10 days of the month with highs well
into the 60s. The temperature roller
coaster continued through the end of the month as highs rebounded to 60°. Daily record highs were set on New Years Day
with highs of 69° at DCA and 68° at IAD. The first 14 days of January temperatures
averaged 10° above normal. The last 15 days of the month averaged 10° below
normal. A five week period starting
late January and lasting into March averaged slightly colder than normal.
Peak day occurred on January 23rd with throughput volume of 1.5
Bcf. Storage level to begin the season
was at 97.6% and at season end was _____.
Projects scheduled for the
summer season include re-setting of 24 line at Leesburg Gate Station which
could be out of service up to 6 weeks.
Rockville station will be out of service for a minimum of 3 weeks for
pigging. During June they will be
performing maintenance of the Middleburg Gate Station while installing SCADA
system to the gate. The new Rock Creek
Gate Station (off of Williams) should be in service by September 2005. Testing dates are scheduled for August. And are starting the design phase of a new
LNG facility at Old Chillum low pressure plant.
AGL Resources Wayne Rutledge reported that VNG had
a throughput of 350 Mmcf on peak day January 23rd. The winter brought many challenges and company was pleased with
accomplishments.
Baltimore G&E Ed Turowski reported conditions were
also slightly warmer than normal with
the exception of March for BG&E.
Peak day also occurred on January 23rd with their 2nd highest send-out
on record.
South Jersey Gas Peak day for South Jersey Gas also
occurred on January 23rd with a throughput of 422,656 Dth per Ed Unger. Three day peak on January 21, 22 and 23
totaled 1,197,541 Dth. Total LNG
vaporized equaled 343,250 Mcf, total LNG boil off was 68,949 Mcf and total LNG
received by truck was 499,107 Mcf.
Capital improvements include completed replacement of LNG boil
off compressor, completed replacement of LNG plant instrument air compressors
and completed 4 miles of 20 350# MAOP main to feed Cape May County.
Planned improvements for 2005 include new station on Transco
system and 7 miles of 24 700# MAOP main from Repaupo to Swedesboro and 4 miles
of 24 350# MAOP main from Mays Landing to McKee City.
Hourly Flows (Power Plants)
The group briefly discussed
the proposed standards approved by a NAESB subcommittee addressing
communications between pipelines and power plants. The executive committee at NAESB will be voting on them in June.
Gale distributed the new password now in effect until the fall
session and informed the group that all sensitive items requiring password
protection will be placed under the ARCHIVES link.
Jim Cosgrove expressed the possibility of Washington Gas hosting
the fall meeting.
The meeting was adjourned at 4:30 p.m.